DESIGNS REVEALED FOR NEW-LOOK BUILDING 6

Construction has started on new spaces for Building 6

SUMMARY:

  • Designs revealed for new teaching and learning space in Building 6
  • Parts of Building 6 are now being closed ahead of construction works

WHEN: August 2011 - February 2012


RELATED:Student Housing Tower; Building 6 Podium Extension

Integrated technology, polished concrete floors, bold colours and exposed finishes define the new-look teaching and learning spaces in Building 6.

The design by architects Gardner Wetherill creates a mixture of formal and informal teaching and learning spaces on levels 3 to 7 of the building's new podium extension. The podium was extended as part of the Student Housing Tower (Yura Mudang) construction.

The design was unveiled to principal users the Design, Architecture & Building Faculty (DAB) at a recent faculty forum.

Demoltion of most spaces is now complete, with construction due to commence in August.



THE DESIGN AT A GLANCE

  • The design is driven by UTS's shift towards a mixture of formal and informal teaching and learning spaces, such as those in the recently completed Building 5 "Green Space"
  • There is a wide variety of new facilities, ranging from large lecture theatres (or general teaching spaces) to small bookable group work areas
  • Specialist facilities will service DAB students studying architecture, design and animation
  • An "industrial chic" aesthetic drives the selection of materials and finishes
  • The podium extension comprises some 5,950m² of new teaching and social spaces

CONSTRUCTION PROGRAM

  • Construction is due to start in August 2011
  • Completion is scheduled for February 2012
  • Some DAB staff have had to relocate to accommodate the construction schedule
  • There will be a closure of the central stair and lifts from 16 December 2011 to 30 January 2012 to allow for upgrade of the existing building's services
  • UTS will provide a detailed construction program to all stakeholders prior to works starting on site
  • UTS Staff can download the project overview, as presented to DAB [pdf, 5.9mb]

BUILDING 6 CAR PARK - TEMPORARY CLOSURE

  • Please note the Building 6 car park will be closed for one day only on Saturday 13 August for line marking.
  • Contact Project Manager Brandon Bell for more information

For more information, visit the project page on the Master Plan website.